The model is designed to test the generator, load, and grid components of the Electrical library.
Simulation sequence:
- t=0 s: The system starts at equilibrium. All power coming from the generator is absorbed by the load, no exchange with the grid.
- t=1 s: The generator torque (hence power) is reduced by 10%; the corresponding amount of power is now drawn from the grid.
- t=3 s: The load power is increased by 10%; the corresponding amount of power is drawn from the grid.
Simulation Interval = [0...5] sec
Integration Algorithm = DASSL
Algorithm Tolerance = 1e-6
Generated at 2024-11-22T19:25:38Z
by OpenModelicaOpenModelica 1.24.2 using GenerateDoc.mos