The model is designed to test the generator and load components
of the Electrical
library.
Simulation sequence:
- t=0 s: The system starts at equilibrium, with the breaker
closed. All the active power produced by the generator is consumed
by the load, so there is zero power drawn from the grid.
- t=1 s: The torque (hence the power) is reduced by 20%; the
corresponding amount of power is now drawn from the grid.
- t=3 s: The load is reduced by 10%, so the power drawn from the
grid is now reduced to 10% of the nominal value.
- t=5 s: The breaker is opened. Since there is a deficit of 10%
nominal power in the formed island, the frequency starts decreasing
with a rate of 10% for each acceleration time Ta=10 s, i.e., by
1%/s, or 0.5 Hz/s.
Simulation Interval = [0...10] sec
Integration Algorithm = DASSL
Algorithm Tolerance = 1e-6
Generated at 2026-04-07T18:18:28Z by OpenModelicaOpenModelica 1.26.3 using