recordExampleGenerationPark
Generation park defining one unit for each type of power plant in the Transient Library
Extends from TransiEnt.Grid.Electrical.Base.PartialGenerationPark (Empty partial generation park).
Information
1. Purpose of model
This record can be used in model that have 8 Types of electric generating units. It contains basic parameterization such as installed power, power gradients etc.
2. Level of detail, physical effects considered, and physical insight
(Purely technical component without physical modeling.)
3. Limits of validity
(Purely technical component without physical modeling.)
4. Interfaces
(no remarks)
5. Nomenclature
(no elements)
6. Governing Equations
(no equations)
7. Remarks for Usage
(no remarks)
8. Validation
(no remarks)
9. References
(no remarks)
10. Version History
Model created by Pascal Dubucq (dubucq@tuhh.de) on Mon Aug 18 2014
Parameters
| Type | Name | Default | Description |
|---|---|---|---|
| String | index (from PartialGenerationPark) | fill("", 0) | Click on edit (little book) to see indexing |
| Integer | nPlants (from PartialGenerationPark) | No. of plants in scenario (including e.g. RE) | |
| Integer | nDispPlants (from PartialGenerationPark) | No. of dispatchable plants (plants that get setpoints) | |
| Integer | nMODPlants (from PartialGenerationPark) | nDispPlants | No. of plants participating in intraday optimization |
| Integer | isMOD (from PartialGenerationPark) | 1:nDispPlants | Index set of plants that get setpoints from merit order dispatcher (intraday optimization) |
| Integer | isFRE (from PartialGenerationPark) | {0} | Index set of fluctuating renewable energy plants |
| Integer | isCHP (from PartialGenerationPark) | {0} | Index set of combined heat and power plants (these have time varying power limits) |
| SI.Power | P_min_MOD (from PartialGenerationPark) | P_min[isMOD] | |
| SI.Power | P_max_MOD (from PartialGenerationPark) | P_max[isMOD] | |
| SI.Frequency | P_grad_max_star_MOD (from PartialGenerationPark) | P_grad_max_star[isMOD] | |
| Real | C_var_MOD (from PartialGenerationPark) | C_var[isMOD] | |
| Modelica.Units.SI.Time | H_gen_CCP | 0 | |
| Modelica.Units.SI.Time | H_gen_BC | 0 | |
| Modelica.Units.SI.Time | H_gen_BCG | 0 | |
| Modelica.Units.SI.Time | H_gen_PS | 0 | |
| Modelica.Units.SI.Time | H_gen_WindOn | 0 | |
| Modelica.Units.SI.Time | H_gen_WindOff | 0 | |
| Modelica.Units.SI.Time | H_gen_PV | 0 | |
| Modelica.Units.SI.Time | H_gen_ROH | 0 | |
| Summary | |||
| SI.Power[nDispPlants] | P_max (from PartialGenerationPark) | Maximum power production of dispatchable plants | |
| SI.Power[nDispPlants] | P_min (from PartialGenerationPark) | Minimum power production of dispatchable plants | |
| SI.Frequency[nDispPlants] | P_grad_max_star (from PartialGenerationPark) | Maximum power gradient with respect to nominal capacity (1/3600 s means full load in 1 hout) | |
| TransiEnt.Basics.Units.MonetaryUnitPerEnergy[nDispPlants] | C_var (from PartialGenerationPark) | Variable cost vector of dispatchable plants in MTU per Energy | |
| SI.Power | P_total (from PartialGenerationPark) | sum(P_max) | Sum of installed capacity in generation park |
| Installed capacity, dispatchable units | |||
| Modelica.Units.SI.Power | P_el_n_NUC | 300e6 | Installed capacity of nuclear plant |
| Modelica.Units.SI.Power | P_el_n_BCG | 781.6e6 | Installed capacity base load, i.e. brown coal, nuclear and waste incinerator plants |
| Modelica.Units.SI.Power | P_el_n_BC | 540.1e6 | Installed capacity black coal |
| Modelica.Units.SI.Power | P_el_n_CCP | 408e6 | Installed capacity combined cycle plants |
| Modelica.Units.SI.Power | P_el_n_GT | 90.9e6 | Installed capacity gas turbines |
| Modelica.Units.SI.Power | P_el_n_OIL | 99e6 | Installed capacity mineral oil plants |
| Modelica.Units.SI.Power | P_el_n_OILGT | 31e6 | Installed capacity mineral oil plants |
| Modelica.Units.SI.Power | P_el_n_GAR | 39e6 | Installed capacity garbage plants |
| Modelica.Units.SI.Power | P_el_n_PS | 157.3e6 | Installed capacity pumped storage |
| Modelica.Units.SI.Power | P_el_n_BM | 90.9e6 | Installed capacity biomass |
| Installed capacity, fluctuating sources | |||
| Modelica.Units.SI.Power | P_el_n_WindOn | 758.9e6 | Installed capacity onshore wind |
| Modelica.Units.SI.Power | P_el_n_WindOff | 6.88e6 | Installed capacity offshore wind |
| Modelica.Units.SI.Power | P_el_n_PV | 734.9e6 | Installed capacity photovoltaic |
| Modelica.Units.SI.Power | P_el_n_ROH | 90.9e6 | Installed capacity runoff hydro plants |
| Physical Constraints › Minmum Power | |||
| Real | P_min_star_NUC | 0.2 | Dimensionless minimum power gas turbines |
| Real | P_min_star_GT | 0.2 | Dimensionless minimum power gas turbines |
| Real | P_min_star_CCP | 0.2 | Dimensionless minimum power combined cycle plants |
| Real | P_min_star_BC | 0.3 | Dimensionless minimum power black coal |
| Real | P_min_star_BCG | 0.4 | Dimensionless minimum power base load, i.e. brown coal, nuclear and waste incinerator plants |
| Real | P_min_star_PS | 0 | Dimensionless minimum power pumped storage |
| Real | P_min_star_BM | 0.2 | Dimensionless minimum power biomass |
| Real | P_min_star_ROH | 0 | Dimensionless minimum power runoff hydro plants |
| Real | P_min_star_OIL | 0.2 | Dimensionless minimum power mineral oil plants |
| Real | P_min_star_GAR | 0.2 | Dimensionless minimum power garbage plants |
| Physical Constraints › Maximum power gradient | |||
| Real | P_grad_max_star_NUC | 0.2/60 | Dimensionless maximum power gradient gas turbines |
| Real | P_grad_max_star_GT | 0.12/60 | Dimensionless maximum power gradient gas turbines |
| Real | P_grad_max_star_CCP | 0.1/60 | Dimensionless maximum power gradient combined cycle plants |
| Real | P_grad_max_star_BC | 0.08/60 | Dimensionless maximum power gradient black coal |
| Real | P_grad_max_star_BCG | 0.06/60 | Dimensionless maximum power gradient base load, i.e. brown coal, nuclear and waste incinerator plants |
| Real | P_grad_max_star_PS | 1/60 | Dimensionless maximum power gradient pumped storage |
| Real | P_grad_max_star_ROH | 0.12/60 | Dimensionless maximum power gradient runoff hydro plants |
| Real | P_grad_max_star_BM | 0.12/60 | Dimensionless maximum power gradient biomass |
| Real | P_grad_max_star_OIL | 0.12/60 | Dimensionless maximum power gradient mineral oil plants |
| Real | P_grad_max_star_GAR | 0.12/60 | Dimensionless maximum power gradient garbage plants |
| Physical Constraints › Inertia | |||
| Modelica.Units.SI.Time | H_gen_ST | 10 | Inertia constant typical steam turbine |
| Modelica.Units.SI.Time | H_gen_GT | 12 | Inertia constant typical gas turbine |
| Modelica.Units.SI.Time | H_gen_CCGT | H_gen_GT/3 + 2*H_gen_ST | Inertia constant typical combined cycle plant |
| Modelica.Units.SI.Time | H_gen_HT | 12 | Hydroturbine |
| Modelica.Units.SI.Time | H_gen_BM | 10 | Inertia constant biomass (gas motor) |
| Modelica.Units.SI.Time | H_gen_RE | 0 | Inertia constant onshore wind |
| Other properties › Efficiency | |||
| Modelica.Units.SI.Efficiency | eta_el_n_NUC | 0.35 | Mean electric efficiency nuclear plants |
| Modelica.Units.SI.Efficiency | eta_el_n_GT | 0.35 | Mean electric efficiency gas turbines |
| Modelica.Units.SI.Efficiency | eta_el_n_CCP | 0.52 | Mean electric efficiency combined cycle plants |
| Modelica.Units.SI.Efficiency | eta_el_n_BC | 0.4 | Mean electric efficiency black coal |
| Modelica.Units.SI.Efficiency | eta_el_n_BCG | 0.34 | Mean electric efficiency base load, i.e. brown coal, nuclear and waste incinerator plants |
| Modelica.Units.SI.Efficiency | eta_el_n_BM | 0.35 | Mean electric efficiency biomass |
| SI.Efficiency | eta_el_n_OIL | 0.40 | Mean electric efficiency mineral oil plants |
| SI.Efficiency | eta_el_n_GAR | 0.16 | Mean electric efficiency garbage plants |
| Other properties › Variable Costs for Optimization | |||
| Real | C_var_NUC | 8 | Variable cost in arbitrary units |
| Real | C_var_GT | 10 | Variable Cost in arbitrary units, gas turbines |
| Real | C_var_CCP | 8.6 | Variable Cost in arbitrary units, combined cycle plants |
| Real | C_var_BC | 12 | Variable Cost in arbitrary units, black coal |
| Real | C_var_BCG | 12 | Variable Cost in arbitrary units, base load, i.e. brown coal, nuclear and waste incinerator plants |
| Real | C_var_PS | 12 | Variable Cost in arbitrary units, pumped storage |
| Real | C_var_WindOn | 0 | Variable Cost in arbitrary units, onshore wind |
| Real | C_var_WindOff | 0 | Variable Cost in arbitrary units, offshore wind |
| Real | C_var_PV | 0 | Variable Cost in arbitrary units, photovoltaic |
| Real | C_var_BM | 10 | Variable Cost in arbitrary units, biomass |
| Real | C_var_ROH | 10 | Variable Cost in arbitrary units, runoff hydro plants |
| Real | C_var_OIL | 10 | Variable Cost in arbitrary units, mineral oil plants |
| Real | C_var_GAR | 10 | Variable Cost in arbitrary units, garbage plants |