modelNetwork_Expanded
Extended network for testing resynchronization of a generation unit to a weak grid
Extends from Modelica.Icons.Example (Icon for runnable examples).
Information
This example system shows how the resynchronization controller is used to connect Generator 2 back to the grid. Note that at 2 seconds, a signal is triggered to equalize voltage magnitudes on buses 3 and 4.
Simulate the system for 50 seconds. Variables of interest are:
B3.vB4.vG1.gen.SPEEDG2.gen.SPEED
Note the behavior of those variables before and after the connection of generator G2 to the main grid.